Time Lines for Processing of DPMS Applications

Sl.NO Feature Time Lines
1 Building Permissions 30 Days
2 Draft Layout Permissions 30 Days
3 Change Of Land Use 30 Days
4 NOCs 30 Days
Sl.NO Description TIME LINES(IN DAYS) AS RECOMMENDED BY ASCI
Building Permissions Layout Permissions CLU NOC
1 Application receipt & File development 5 5 5 5
2 Title Scrutiny 3 3 3 3
3 Technical Scrutiny & Site Inspection by JPO/ APO 6 6 6 6
4 Technical Approval by PO, CPO & Director Planning 7 7 7 7
5 MC Approval 4 4 4 4
6 Issue Of DC Letter to Applicant 3 3 3 3
7 After Payment of Fee, issue of final proceedings 2 2 2 2
Total 30 30 28** 30

* Remarks furnished to Govt.
** Issue of final proceeding depends on further communication from Government.